Excavation work has started on Majanankatu

Excavation work started in Karhukallio

Release
24.8.2021 12:52
Access to Majavankatu from the direction of Lempeenliettentie is closed and takes place along a detour.

The actual excavation work for the water supply and street renovation of Karhukallio started on Monday, August 23.8.2021, XNUMX. The streets to be renovated are Majavankatu, Hiirenkuja, Pitsiinkorventie and Myyränkuja.

The works started at the intersection of Majavankatu and Lempeenliettentie and are progressing towards Hiirenkuja.

Initially, access to Majavankatu from the direction of Lempeenliettentie is closed. The houses on Majavankatu and Hiirenkuja are transported along the detour, which was built in the forest section between Myyränkuja and Hiirenkuja. 

Preliminary schedule of the renovation:

  • Majavankatu and Hiirenkuja 08/21 – 12/21
  • Pitsiinkorventie and Myyränkuja 04/22 – 06/22

More information

Jarkko Lapatto, Koneurakointi Ovaska Oy, tel. +358408571633