Picture
Asemäenti underpass

Work obstructing traffic at the Asemäki underpass tunnel construction site 11.11.

Release
7.11.2019 17:03

On 11.11.2019 November 3,7, NRC Group Finland Oy will carry out works causing traffic problems at the Asemäki underpass bridge site on Karhumäenkatu. During the day, the girders of the bridge stand are lifted into place and the underpass height of the bridge changes to XNUMX meters. Traffic controllers stop traffic from time to time during the lifting work.

- The unusual traffic arrangement, i.e. the changed underpass height, is estimated to be in use on 11.11. - between 31.12.2019 December XNUMX, says the foreman Antero Pyykkönen.

More information: responsible foreman Antero Pyykkönen NRC Group Finland Oy phone 040 864 5739.