Picture

Resources and implementer
No additional resources required. Responsible party Imatran Lämpö Oy and partners.
Meter
Implemented: yes/no.
Schedule
2021-2024
Effect of the procedure
The recovery of waste heat reduces the need for fuels in the production of district heat.
Situation in May 2022:
Contract negotiations in progress for one of the partner companies.
A preliminary investigation is underway at one of the partner companies.
Discussions started with one partner company.